Public Utilities Reports

PUR Guide 2012 Fully Updated Version

Available NOW!
PUR Guide

This comprehensive self-study certification course is designed to teach the novice or pro everything they need to understand and succeed in every phase of the public utilities business.

Order Now

Watts Bar Goes on Line

Fortnightly Magazine - January 15 1996

The Nuclear Regulatory Commission (NRC) has authorized the Tennessee Valley Authority (TVA) to load fuel and perform low-power testing of the Watts Bar nuclear plant. The low-power license will allow the 1,160-megawatt Unit 1 to operate at 5 percent of capacity. The license verifies that Watts Bar construction is complete, and that all safety and environmental requirements have been met. A license to operate at full power may be granted once the fuel loading and low-power testing is complete. Commercial operation is anticipated for spring 1996. TVA has not yet decided whether to complete Watts Bar Unit 2.

41

Articles found on this page are available to Internet subscribers only. For more information about obtaining a username and password, please call our Customer Service Department at 1-800-368-5001.