Chesapeake Bay

FERC to Issue Environmental Assessment for Dominion Cove Point LNG Project on May 15

Dominion received word from the Federal Energy Regulatory Commission (FERC) that the agency will issue its environmental assessment for the Dominion Cove Point LNG liquefaction and export project on May 15. The proposed export facility will be within the 131-acre footprint of the LNG import facility. No new pipelines, storage tanks or piers are needed at the facility. The company needs about 50 permits and approvals before construction can begin.

Panda Power Funds to Build 859 MW Power Plant in Maryland

Panda Power Funds intends to build, own and operate an 859-MW combined-cycle power plant in Brandywine, Maryland. The Mattawoman plant will also be a “zero-liquid-discharge” plant, returning no waste water to a treatment facility and subsequently prevents the discharge into the Chesapeake Bay. Construction of the Mattawoman project will take approximately 30 months and is dependent upon financing, regulatory approvals and other conditions.