AWS Truepower Contracted as Lender Engineer for Financing of the Largest Wind Farm in Mexico

AWS Truepower was hired to act as independent engineer to support the financing and construction of the Ventika I & Ventika II wind projects in Nuevo Leon, Mexico. The Ventika Wind Project consists of two 126-MW wind projects, for a total capacity of 252 MW, making it the largest wind project in Mexico at the time of financing. The total investment for the projects is $650 million, secured by co-developers CEMEX and Fisterra Energy. AWS Truepower acted as the energy consultant and engineer in the debt financing for the project, and is providing construction monitoring on behalf of the lenders and project sponsors through to substantial completion of the projects, expected in the second quarter of 2016. The Ventika I and Ventika II projects will utilize 84 Acciona AW 3000 wind turbines. Construction began in the second quarter of 2014 and commercial operation is expected by the second quarter of 2016.