Vaughan Woodruff is Regulatory Vice President at the Interstate Renewable Energy Council (IREC). Sky Stanfield represents IREC in state regulatory proceedings and is a partner at Shute, Mihaly & Weinberger, LLP.
Limited generation profiles (LGPs) and limited load profiles (LLPs) are emerging approaches that can enable the integration of more generation or load on the distribution grid without the need for costly and time-consuming upgrades or study processes. As regulators and utilities grapple with unprecedented load growth as well as clean energy and climate goals, LGPs and LLPs can offer a cost-effective and rapid solution.
Vaughan Woodruff, Regulatory Vice President at the Interstate Renewable Energy Council (IREC), spoke with Sky Stanfield, an attorney who has been deeply involved in the first state implementation of these regulatory tools, to learn more. Stanfield represents IREC in state regulatory proceedings and is a partner at Shute, Mihaly & Weinberger, LLP.
IREC’s Vaughan Woodruff: What are limited generation profiles?
Sky Stanfield: Limited generation profiles, or LGPs, allow interconnection applicants to propose a defined export schedule for their project that would limit export during periods when the grid is constrained.
By doing this, a distributed energy resource (DER) project, like a solar array or an energy storage system, can avoid distribution system impacts and the need for grid upgrades. In most cases, they can also interconnect quickly using a fast-track screening process and avoid lengthy study processes usually required for projects that exceed current system constraints.
IREC: Where have limited generation profiles been used to date, and how do they work?
Sky Stanfield: The concept of limited generation profiles was first developed in California. While some states are exploring more complicated flexible interconnection programs, which would require DER communications interfaces to direct DERs to respond to changing grid conditions, those programs are still in their early days. In the U.S., the more simplified fixed schedule approach of an LGP has only been rolled out in California so far.
In March 2024, the California Public Utilities Commission revised the state’s interconnection procedures to integrate limited generation profiles, allowing interconnection applicants the option of submitting an export schedule. As of July of this year, California customers can now propose a project with a limited generation profile in their interconnection application.
California’s LGP relies on the state’s hosting capacity analysis or integration capacity analysis, as it’s known in California. A hosting capacity analysis is a publicly available tool that identifies the amount of DER capacity (or load) that can be connected without requiring distribution system upgrades.
This allows the applicant to see specifically how much export capacity can be accommodated at the node on the distribution system where they’re proposing the project — and how that varies throughout the day and month by month. That informs how much capacity the project can export in specific hours without triggering the need for a study or system upgrade. From this, the applicant can propose an LGP that stays within those limits.
IREC: Why might regulators and utilities want to consider LGPs?
Sky Stanfield: LGPs offer many benefits. For interconnection customers, LGPs enable applicants to design DER systems that are optimized to the available grid capacity and avoid major upgrade costs.
That makes projects more affordable and may open up sites that were previously inaccessible because they would have triggered a cost-prohibitive upgrade that may have only been needed for a limited period of time each year. Another major benefit is that customers can gain interconnection approval much more quickly.
There are also benefits to state governments, ratepayers, and even utilities. Distribution upgrades typically take a long time and are expensive. This creates barriers to states’ and utilities’ efforts to interconnect new generation and burdens ratepayers with higher costs for energy supply as a result.
Additionally, there’s long been a desire to make DERs more responsive to grid constraints. We would like more energy supplied when demand is high and less supplied when we don’t need it. LGPs address all of these needs.
Finally, there are currently significant supply constraints for certain equipment, like transformers. This shortage is likely to significantly impair clean energy deployment. Allowing customers to use LGPs is a way of working around the transformer shortage, in particular.
IREC: There is a similar concept for load. Can you explain what a limited load profile is?
Sky Stanfield: Just as a hosting capacity analysis can model how much generation the grid can accommodate at different nodes at different times, it can model the same data for load. Based on identified load constraints, a customer could interconnect using a similar profile that establishes a schedule for how much load they will use at different times, providing the utility with assurances that the load will align with system constraints.
Right now, there is enormous and unprecedented load growth. Data centers and AI are bringing significant amounts of load onto the grid in a rapid fashion that’s unprecedented in our lifetimes.
Electric vehicle charging infrastructure is another source of significant load growth, especially in the case of chargers for medium- and heavy-duty vehicles. This load growth creates a number of challenges, particularly in building the capacity upgrades for the grid to accommodate those projects.
Historically, when utilities needed to accommodate that level of load, they could engage in planning over many years before a new subsidized line was built. That time frame doesn’t align with either our electrification goals or the energy needs of data centers. Limited load profiles offer one pathway to get customers online with some capacity, based on current system constraints.
IREC: What is the current application of limited load profiles in the U.S.?
Sky Stanfield: California has an open proceeding related to limited load profiles, the energization timelines proceeding. The Commission is considering whether to adopt some sort of flexible service connection or limited load profile policy for each of the major utilities in California.
Both Southern California Edison and Pacific Gas and Electric are currently already allowing load projects to adopt a profile or schedule as a bridging solution when upgrades are needed. In the current form, that profile is not based on the utility’s hosting capacity analysis, so the schedules are rougher and less precise than if they were based on that data.
One debate in this proceeding is whether limited load profiles should be a long-term solution for customers or just a bridging solution. For example, consider a customer building an electric vehicle charging site that ultimately needs five megawatts of demand, but only three megawatts of demand are currently available — or maybe there are five megawatts on Tuesdays at four p.m., but not all the time.
That customer could agree to a schedule while the utility builds the upgrades to ultimately deliver five megawatts all the time. That may be ideal for the customer, but perhaps less ideal for ratepayers.
There is broad agreement that a bridge solution is needed, but some parties, including IREC, are interested in exploring whether there is also an opportunity to encourage customers who have the flexibility, to be willing to agree to a longer-term schedule, thus limiting the total number of grid upgrades needed. It remains to be seen how the Commission will rule.
IREC: What role do you think limited generation profiles and limited generation profiles can play in how regulators and utilities respond to changing grid dynamics – from the rise of generative AI and data centers to increased electric vehicle charging?
Sky Stanfield: Although there has been massive growth of clean energy over the past decade and significant work to electrify loads historically powered by other sources, comparably little has been done to align clean energy generation and load. For years, utilities have expressed concern that DERs do not respond to grid conditions. These approaches are our chance to enable that, to make load and generation more collaborative and reduce the total amount of grid investment needed.
When it comes to load growth in particular, the biggest challenge is simply building the grid upgrades at the necessary pace and supporting the associated costs. LLPs are an easy way to both get projects on the grid quicker and lower the costs
Furthermore, LGPs and LLPs don’t require the much more significant investments needed for other forms of flexible interconnection or flexible service connections. There are many approaches to flexible interconnection and flexible service connections – from full-scale DERMS deployment requiring millions of dollars of utility investment, to LGPs and LLPs that do not require direct communication with DERs. Commissions have options; LGPs and LLPs are the easiest to implement in the near term.