D.C. Commission Order Eyes Interconnections
David Golembeski is a Senior Program Manager for the Interstate Renewable Energy Council’s Regulatory Team.
On November 26, 2025 the Public Service Commission of the District of Columbia issued an order establishing a temporary program to ensure interconnection delays do not prevent clean energy projects from qualifying for tax credits that are being phased out as a result of H.R. 1, the One Big Beautiful Bill Act (OBBBA).
In the order, the PSC recognized that “without immediate, temporary process adjustments, a substantial portion of District customers may lose access to federal tax benefits, leading to higher system costs and reduced solar adoption at a time when legislative and policy mandates call for accelerated growth in distributed energy.” In response, the PSC established a Temporary Conditional Interconnection Program (TCIP).
The program addresses steps in the utility interconnection process for customer-owned solar and energy storage projects that could cause delays and result in customers of the Potomac Electric Power Company (Pepco) missing critical deadlines for eligibility for remaining federal tax credits.
Federal Tax Credit Changes
H.R. 1 terminated several key energy tax credits for residential and commercial taxpayers. These changes accelerated the construction and utility interconnection timeline requirements for projects seeking to leverage those federal tax credits.
Residential Solar and Energy Storage Systems. The most immediate tax credit consequence of H.R. 1 was the termination of the Section 25D residential clean energy credit effective January 1, 2026. This provision provided a thirty percent tax credit for qualified projects — including residential solar electric and energy storage systems. It was regularly utilized by residential utility customers for systems they purchased and owned.
The sunset of the Section 25D tax credit does not impact the tax credit treatment of third party-owned residential projects. Third party-owned systems, such as those in which a company leases the equipment to the homeowner, do not use the Section 25D tax credit. Instead, the companies that own these assets leverage the Section 48E clean energy investment credit, which has a later expiration date under OBBBA. These systems are eligible for federal tax credits through December 31, 2027.
Commercial and Community Energy Systems. Customer-owned and third party-owned commercial and community solar energy systems also regularly utilize the Section 48E tax credit. Like third party-owned residential systems, these systems must be “placed in service” by December 31, 2027, to leverage remaining federal tax incentives.
Alternatively, projects that meet federal requirements for starting construction by July 4, 2026, will have up to four years from the start of construction to be placed in service and retain tax credit eligibility. This means that tax credit-eligible projects could be built through mid-2030.
While H.R. 1 accelerated the deadlines for tax credit eligibility for commercial solar projects, the Section 48E credits for energy storage systems do not have a deadline and remain in place.
Role of Utilities in Federal Tax Credit Eligibility
A key consideration for tax credit eligibility is ensuring that the project is placed in service prior to the termination dates. For the Section 48E credit, the threshold for demonstrating a project has been placed in service is commonly the utility’s issuance of permission to operate.
This provision makes taxpayers reliant on timely work by their contractor and utility to be able to access the tax credits. If construction or utility interconnection — potentially including distribution grid upgrades — stretch beyond the tax credit deadlines, customers will lose out on tax credits equal to thirty percent of the project cost.
How D.C. PSC’s Order Addresses These Issues
One of the focal points of the PSC order is alleviating the potential impacts of utility delays on the placed-in-service requirements. The TCIP requires Pepco to provide conditional approval to projects awaiting grid upgrades that are unlikely to be completed ahead of looming tax deadlines. The intent of this provision is to provide customers with documentation needed to satisfy placed-in-service requirements.
Projects that require grid upgrades can now be interconnected before those upgrades are complete, on the condition that they limit the amount of energy they export to the grid until the completion of grid upgrades to accommodate their full export capacity (upgrades must be completed by the June 30 program end date). The order also directs Pepco to work with Commission Staff and other parties to develop a phased interconnection agreement that more formally standardizes this process.
The Commission also established a requirement that Pepco provide customers with permission to operate within twenty days of submission of a complete interconnection application for projects that do not export to the grid or limit their export based on known grid constraints.
Additionally, the PSC authorized Pepco to “implement temporary staffing measures” through mid-2027 or later to accelerate the utility’s review processes. This decision responds to parties’ assertion that “[a]dditional Pepco staffing, particularly interconnection engineering resources, is necessary on a near-term, temporary basis to process ATI [Authorizations to Install] and ATO [Authorization to Operate] requests at the anticipated scale.”
Together, these measures address timeline concerns expressed by parties in D.C. and provide a strong model for approaches that regulators in other jurisdictions can consider to ensure interconnection delays do not preclude customers from accessing valuable tax benefits.
Other Considerations Addressed by the PSC
In addition to directly addressing key considerations related to placed-in-service requirements, the PSC order requires Pepco to increase reporting frequency on its interconnection queue. Pepco will be required to provide bimonthly reports until June 2026 to provide the PSC with the data needed to assess its performance in getting projects approved and online during the most consequential period for projects seeking to meet the July 4, 2026 start-of-construction requirements or the December 31, 2027 placed-in-service deadline.
The order also directs Pepco to begin construction of grid upgrades as soon as the customer has made the necessary payments, and to develop a plan to maintain an adequate stock of equipment commonly required to facilitate interconnection, to avoid unnecessary procurement delays.
Finally, and importantly, the PSC recognized that more work is needed to advance the priorities addressed by this order. It directed Commission staff to continue to refine interconnection processes, consider ways to streamline the resolution of interconnection disputes, and make specific provisions of the TCIP permanent.
Takeaways for Regulators in Other Jurisdictions
The actions taken by the D.C. PSC address interconnection challenges that states around the country are confronting. They also align with priorities identified by utility regulators and governors’ offices in Arizona, California, Colorado, Delaware, Maryland, Massachusetts, New York, and Washington following the enactment of H.R. 1.
The D.C. PSC has demonstrated how a two-prong approach of creating an immediate, temporary program to expedite interconnection, coupled with ongoing reform, can help states leverage remaining federal tax credits to get more generation online to address resource capacity concerns. This approach is a strong model for how utility regulators can limit material harms to customers from inefficient interconnection processes or utility noncompliance with regulatory timelines — harms that can be particularly acute with expiring tax credits on the line.