GE received an order from the Tennessee Valley Authority (TVA) to supply two high-efficiency 7HA.02 gas turbine generators for the new combined-cycle Allen plant. The new plant will replace three coal-fired units that are being retired as TVA works toward a December 2018 deadline from the U.S. Environmental Protection Agency (EPA) to reduce coal emissions. The TVA Allen plant will have the capacity to generate 1,000 MW of power in combined-cycle mode, the equivalent power that would be needed to supply 1 million U.S. homes. The gas turbines are expected to be delivered to the site in August 2016 with commercial operation planned for May 2018.